Office: (281) 494-1199 Fax: (281) 242-9060 meyersan@co.fort-bend.tx.us andy@andymeyers.com 1809 Eldridge Road Sugar Land, Texas 77478
Your Privacy Is At Risk:I strongly believe that a primary focus of government officials should be on protecting the privacy of our citizens, not on protecting other elected officials at the expense of our citizens’ privacy rights. Read More
PRECINCT 3 ONLY
Project ID
Project Name
From – To Limits
Project Description / Cost in $ Million
Construction Starts
703
Falcon Landing Boulevard
Greenbusch Road – Katy Gaston Road
New location 4-lane curb and gutter boulevard with storm sewer. ($6.0 Total / $3.5 FBC)
Phase 1 Fall '09
719
Burney Road
West Airport Boulevard – Old Richmond Road
Rehabilitate existing 2-lane rural roadway and add shoulders. ($2.25 FBC)
Est. Summer '10
732
Greenbusch Road
Falcon Landing Boulevard – Katy Flewellen
Reconstruct to 4-lane curb and gutter with storm sewer. ($11.25 FBC)
Est. Summer 2010
733
Katy Gaston Road
Cinco Ranch Boulevard – FM 1093
Reconstruct to 4-lane roadway. ($8.75 FBC)
Est. Spring 2010
734
Katy Flewellen Road
Pin Oak Road – Katy Gaston Road
Construct 4-lane curb and gutter with storm sewer. ($7.5 FBC)
735
Mason Road
FM 359 – SH 99
Construct 4-lane with storm sewer; partial new location with Skinner Lane ($9.2 Total / $6.1 FBC)
Spring 2010
735A
Mason Road Bridge
At Oyster Creek
739
Beechnut Road
Fort Bend ISD – Harlem Road
New location 4-lane w/ storm sewer. ($1.5 FBC)
TBD
741
West Bellfort Road
Harlem Road – SH 99
New location 4-lane roadway. ($2.35 FBC)
Developer Timeline
745
Florence Road
Eldridge Road – Burney Road
Purchase ROW, study outfall improvements, improve ditches, and add shoulders. ($1.5 FBC)
Project on Hold
748
FM 1093
SH 99 – FM 1463
Purchase Metro ROW for the expansion of FM 1093 to 4 lanes
720
Dulles Ave
Ave. E – US 90A
Construct 6-lane concrete. Improve capacity at intersections from SH 6 to Ave. E. ($7.7 Total / $4.3 FBC / $0.4 Sugar Land / $2.5 TxDOT)
Determined by Sugar Land
762
Kingsland Boulevard (City of Katy)
Medical Center Drive – Willow Fork Road
New location 4-lane curb and gutter boulevard with storm sewer. ($1.0 Total / $0.5 FBC)
Completed
PRECINCT 3 (SHARED WITH PRECINCT 4)
Project Description
725
Harlem Road
US 90A – Plantation Drive
Reconstruct to 4-lane asphalt roadway. ($5.5 FBC)
726
Plantation Drive – SH 99
Tx. Dept of Justice Timeline
727
SH 99 – Beechnut Street
Reconstruct to 4-lane asphalt roadway. ($5.2 FBC)
730
Old Richmond Road
SH 6 – Gaines Road
Purchase ROW, rehabilitate existing pavement, and add shoulders. ($1.75 FBC)
731
Martinez Street – FM 1464
New location 4-lane open ditch roadway. ($5.5 FBC)
Under Construction